West Quarna 1 Oilfield | ||
---|---|---|
Electrical Infrastructure Installation | ||
Client Name | ExxonMobil | |
Project Location | WQ1 | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2020 |
Zubair Oilfield Development Project | ||
---|---|---|
Installation of Piping and Pipeline | ||
Client Name | ENI/ZFOD | |
Project Location | Zubair Oilfield, Basrah | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2020 |
CPF Phase 2 Badra Oilfield | ||
---|---|---|
Mechanical,Electrical,Insrtrumentationa and Piping works at Badra Oil Field | ||
Client Name | Samsung/GPNB | |
Project Location | Badra Oilfield—Waset—Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2020 |
Provision of General Construction Consultancy Services | ||
---|---|---|
Provision of general construction consultancy services to the Rumaila supply base, in Iraq | ||
Client Name | Bp Iraq N.V | |
Project Location | North Rumaila/ Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2020 |
Operation and Maintenance Contracts for Badra Oilfield | ||
---|---|---|
1. Provisions of competent, experienced and a professional manpower and equipment/vehicle as further described in this scope of service to support: • Pre commissioning • Commissioning • Maintenance • Shutdown activities • Scaffolding Services |
||
Client Name | Petrofac International (UAE) LLC . | |
Project Location | Badra Oilfield—Waset—Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2020 |
Slug Catcher Project _NR-Basra-Iraq | ||
---|---|---|
Hvac Works For Control & Substation Buildings :Supply And Install Galvanzied Steel With Corosion Resistance Coating And Insect Screen, Galvanized Steel Frame, Blade & Accesoreis. Stainless Steel Frame, Blade & Accessories, Low Leakage Type, Amca Class Ii (Min.) | ||
Client Name | CCC/Shell | |
Project Location | North Rumaila/ Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2019 |
Slug Catcher Project _NR-Basra-Iraq | ||
---|---|---|
Electrical and Instrumentation Work (Cable laying,Cable tray & Cable support Installation,cable termination,Instumentation Works) | ||
Client Name | CCC/Shell | |
Project Location | North Rumaila/ Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2019 |
(modular Building Installation Iraq West Qurna I) Mod075 | ||
---|---|---|
Installation of prefabricated steel structural buildings for LCR ,LER ,Gurd House and four guard towers each one consist of three stories. The project is located in WQ1, the work includes but not limited steel structure installation, electrical work, cable try installation, HVAQ system installation, G&F system. |
||
Client Name | Sajer / Saipem | |
Project Location | West Qurna/ Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2019 |
Mechanical Cleaning for static equipment at KAZ plant | ||
---|---|---|
Client Name | Technip- BGC | |
Project Location | Basra- Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2019 |
Modular Building Installation Iraq West Qurna I (m095) Ds7 Isbl Water Injection System | ||
---|---|---|
Installation of prefabricated steel structural building for LCR ,The project is located in WQ1, the work includes but not limited steel structure installation, electrical work, cable try installation, HVAQ system installation, G&F system | ||
Client Name | Sajer / Saipem | |
Project Location | West Qurna/ Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2019 |
Supply and install of Scaffolds. | ||
---|---|---|
Providing various required Scaffolding along with required skilled manpower, Scaffolding materials. The scope will start from mobilization/ demobilization of skilled & experienced manpower, required scaffolding materials, equipments, tools & tackles to COMPANY site for erecting or dismantling of Scaffolding as per COMPANY Scaffolding procedures and permit requirements and the types of scaffolding is including but not limited to the following : 1. Supply and install Tube and Coupler cantilever scaffolding type. 2. Supply and Install Tube and Coupler suspendable scaffolding Type. 3. Supply and install Tube and Coupler mobile Scaffolding type. 4. Supply and install Tube and Coupler Tower scaffolds type. |
||
Client Name | Technip /BGC/ Shell | |
Project Location | Khor Azubair Gas Plant - Basra - Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2019 |
Installation of ME&I works at Zubair Oil Field | ||
---|---|---|
Installation of Mechanical, Electrical and Instrument works such as vessels, pumps, electrical panels, etc. | ||
Client Name | STX/SOC | |
Project Location | Zubair Oil field - Basra- Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2019 |
Hydro test and Pneumatic test at CPF | ||
---|---|---|
Hydro test and Pneumatic test at CPF | ||
Client Name | Petrofac | |
Project Location | Badra Oilfield / Waset / Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2018 |
Mechanical, Electrical and Instrument works. | ||
---|---|---|
Installation of Mechanical, Electrical and Instrument works such 1. Static Equipment Installation 2. Rotary Equipment Installation 3. Piping Installation 4. Valves Installation 5. Supports 6. NDT 7. Hydro-Test 8. Sand Blast 9. Painting 10. Flushing 11. Pre commissioning 12. Cable Installation 13. LV Transformer 14. ML Transformer 15. Electrical Equipment Installation 16. Electronic Equipment Installation 17. Power Panels 18. Power Generator Installation |
||
Client Name | Petrofac International (UAE) LLC . | |
Project Location | Badra Oilfield—Waset—Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2018 |
Fire Protection Concrete | ||
---|---|---|
Providing all the requirement and manpower to provide 125m3 + 175 m3 of Fire Protection Concrete | ||
Client Name | Albilal Company | |
Project Location | Hamar Mushrif and Azubair Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2018 |
Flow line and piping system for Gas compressor station | ||
---|---|---|
Fabrication, welding and installing flow line and piping system will all pipe fittings at Hamar Mushrif gas compressor station Basra - Iraq | ||
Client Name | BGC Shell - Iraq | |
Project Location | Hamar Mushrif/ Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2018 |
(FCP) Garraf Oil and Gas project in Nassriya | ||
---|---|---|
First Commercial and Production (FCP) Garraf Oil and Gas project in Southern Iraq. The project includes the EPC of storage tanks and the construction of piping systems, process units, LP & ATM. The current FCP Garraf project is designed for 100kbpd oil from the Mishrif formation utilizing two (2) oil processing trains of 50 kbpd capacity each. | ||
Client Name | Lakeshore Toltest Corporation | |
Project Location | Nasrya/ Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2018 |
Garraf Oil and Gas Project | ||
---|---|---|
The project is EPCC of the export pipeline for Garraf Contract Area to export the crude oil from the FCP at Garraf to Ahdep Pipeline which exports the crude oil further to the government depot at Nasseryah city.The project consists of 8km of 18" pipeline with the related facilities such as fiber optic, leak detection system, launching and recieving stations, 2 block valve stations and the required tie-ins. | ||
Client Name | Petronas Caligari Iraq Holding B.V. | |
Project Location | Nasrya/ Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2018 |
ME&I at Khor Azubai Gas Unit | ||
---|---|---|
Scope of Work in KAZ area as follow: • Installation and hook-up of gas treatment facility. • Erection of ME&I equipment and structures • Tie-ins in gas treatment facility existing • Interconnecting to gas treatment facility • Installation of power and control cables. • Installation of piping system with all insulation works. |
||
Client Name | KBR | |
Project Location | Basra- Khor Azubair | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2018 |
Al-Sabla of Lining Project,8Km | ||
---|---|---|
Design and construction of Al-Sabla canal of lining and the work is including, excavation, dewatering and pouring concrete | ||
Client Name | Ministry of Water Resource | |
Project Location | Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2017 |
Line Polyethylene Water Pipeline Network 14 Tamoz Street | ||
---|---|---|
Line Polyethylene water pipeline network in the 14 Tamoze street size 500 mm and 450 mm | ||
Client Name | Basra Water Directorate | |
Project Location | Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2017 |
Project to extend the pipeline to isolate a gas station | ||
---|---|---|
Fabrication, welding and laying pipe line with installing manifold and pipe fittings at Majnon Oilfield | ||
Client Name | Shell - Iraq | |
Project Location | Alshamea -Basra | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2017 |
Supply and Install H.V Electrical Equipment | ||
---|---|---|
The installation of 11KV, 22 KV and 33KV, substations. Our services also include CT, PT & LA, Isolators, gantries and towers | ||
Client Name | JCCI/Babil | |
Project Location | Babil—Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2017 |
Emergency Building in Azubair Hospital | ||
---|---|---|
Construction of Emergency building in Azubair Hospital in Basrah Governorate (2000m2) with 2 stories, this project including Excavation and filling, and concrete works for fundation, columes, slabs, … ( more than 2000m3 reinforced concrete) | ||
Client Name | Basrah support rebuild and services committee | |
Project Location | Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2017 |
Al –Shefaa Electrical Power Cable Project-Basra | ||
---|---|---|
Installation of a new electrical network by: Supply & installation of an over head line 200 circular & 38 lattice steel poles. Supply & installation of 10 transformers (Capacity 250KVA) with accessories | ||
Client Name | Mott MacDonald | |
Project Location | Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2017 |
Supply and install 4 unit of water treatment for Hay Al Hussain Water project | ||
---|---|---|
Supplying and install 4 units of water treatment for Hay Al Hussain Water project in Basrah , capacity of each unit is 400 m3/h | ||
Client Name | Basra Water Directorate | |
Project Location | Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2016 |
Bradhyaa Water Project | ||
---|---|---|
Maintenance and Widening Bradhyaa Water Project including supply and install different sizes of pipes, maintenance all water pumps, filters, valves and other works for project success | ||
Client Name | Basra Water Directorate | |
Project Location | Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2016 |
Supplying and install 4 unit of water treatment for Shat Al Arab Water project | ||
---|---|---|
Supplying and install 4 unit of water treatment for Shat Al Arab Water project in Basrah , each unit capacity is 400 m3/h | ||
Client Name | Basra Water Directorate | |
Project Location | Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2016 |
Square Shooting | ||
---|---|---|
Design and construction of Square shoot for 10th battalion in Nasryah. | ||
Client Name | Corps of Engineers | |
Project Location | Nasrya/ Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2016 |
Rehabilitation of AL Garage P.S. and Sewerage Network. | ||
---|---|---|
Rehabilitation of al garage pump station and construction the Administration buildings, Service buildings and generator room ,Site works, Civil works for sewage collecting tank and Warehouse shed | ||
Client Name | Basra Sewer Directorate | |
Project Location | Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2016 |
Karmat Ali Sewerage Network & 2 Sewage Pump Station | ||
---|---|---|
Supply material, equipment and labors to construct a complete packaged sewage treatment plant and standby generator suitable for a population equivalent of 50,000 people as in the design drawings and the specification | ||
Client Name | Basra Sewer Directorate | |
Project Location | Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2016 |
Hay Al Hussain Sewerage Network | ||
---|---|---|
Supply material, equipment and labors to Excavation, supplying and Laying sewer network piping and manholes for Hay Al Hussain | ||
Client Name | Basra Sewer Directorate | |
Project Location | Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2015 |
Al Nwab Al Dubad Water Network | ||
---|---|---|
Supply and install difference size of pipes, Replace unsuitable materials, Reinstatement and other works for successfully finishing project. | ||
Client Name | Basra Water Directorate | |
Project Location | Basra/Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2015 |
Khor Al Zubayar Project | ||
---|---|---|
Design and construction of a pump system with piping for KHOR AL ZUBYAR harbor. | ||
Client Name | Iraqi Tankers Co. | |
Project Location | Khor Al Zubair / Basra/ Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2015 |
Majnon Pipe Line | ||
---|---|---|
Fabrication, welding and laying pipe line and pipe fittings at Majnon Oilfield – Basra - Iraq | ||
Client Name | Shell - Iraq | |
Project Location | Majnon Oilfield – Basra - Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2015 |
Al Shulah Sewage Pump Station Refurbishment | ||
---|---|---|
Supply material, equipment and labors to supplying and install (INLET CHAMBER , TRASH SCREEN, LIFTING CRANES, SUBMERSIBLE PUMPS, PIPING AND FITTINGS ) , including all necessary buildings and fences. | ||
Client Name | Basra Sewer Directorate | |
Project Location | Basra/ Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2015 |
Al Asmai Water Network Project | ||
---|---|---|
Install the water pipes network containing supply and install difference size of pipes, Replace unsuitable materials and other works for successfully finishing project | ||
Client Name | Basra Water directorate | |
Project Location | Basra/ Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2015 |
Rehabilitation of R-Zero Water Treatment Plant 10,000m3/hr | ||
---|---|---|
Rehabilitation of pumps, motors, generators, power and control cables, and electrical panels | ||
Client Name | Water directorate-Basra | |
Project Location | Basra/ Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2014 |
Al Meshraq Pipe Line Project | ||
---|---|---|
Design and construction of water pipe line at Al-Meshraq Area. | ||
Client Name | Mott MacDonald | |
Project Location | Basra/ AlMeshraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2014 |
West Quarna 1 Oilfield | ||
---|---|---|
Paving and repair of Al Tamimiyah Road ,including excavation, filling, grading, compacting, leveling and paving with asphalt, of 10Km length. The works includes concrete works for intersections of 25cm depth and total 1400 m3. | ||
Client Name | Ministry of Municipalities and Public Works | |
Project Location | Basra—Iraq | |
Category | Completed Project | |
Current Progress | Completed 100% | |
Completion Date | 2014 |